New Load-shedding Schedule Effective from Magh 2

By
Advertisement
Effective from Jan 14, 2012. / Magh 2 2068
  • Load-shedding will take place on the given time inside the Kathmandu Valley and 5 minutes after the given time outside the Valley.
  • Depending upon the condition, load-shedding could increase/decrease by one hour.
  • The load-shedding will be two more hours in the areas of the feeders where 40 to 50 per cent of electricity leakage is recorded.
  • The load-shedding will be three more hours in the areas of the feeders where more than 50 per cent of electricity leakage is recorded.



2 comments:

  1. @ pawan you can see group here
    http://nea.org.np/images/supportive_docs/loadsheddingMagh.pdf